Status Report: Final Presentation

For the final presentation, work was split up into different categories. Alden:  Worked on reflection, and evaluation & reporting. He also recorded the demo of the final prototype (2 hours) Timothy: Worked on the evolution of design slides, reflection, and made changes to the final prototype. (2 hours) Sean : Worked on reflection, system concept statement, and reflection. (2 hours) Toni : Worked on reflection, the evolution of design, and design & usability requirements. (2 hours) Some of the challenges were logistics for implementing changes and recording the final demo. Thank you for sticking along with us as we complete the status reports. Hope you finish this semester "alive and breathing". - The Collaboration Station

Status Report - Deliverable 8 (Analysis)

In the second part of deliverable 8, we will analyze our data to figure out the problems with our prototype and fix them before our final prototype. Everyone in the team will work together on the test data analysis document. There are 5 sections in the analysis: overview, data analysis, testing goals, issues and conclusion. Problems: - Finding patterns among a large amount of data collected to spot the problems and acclaims - Everyone has trouble splitting the work Future plans: - Prioritize the problems found - Fix the problems for our final protoytpe - Start working on the final presentation

Status Report - Deliverable 8

In deliverable 8, we will have each team member letting 2 users test our prototype. We will have our consent forms read and signed by our participants. We will observe them interact with our prototype, take notes, time the process, listen to their complains and acclaims, and rate the usability aspects of the prototype. After gathering all the data, we will start analyzing them to find out the problems, and plot the design improvement plan for our final prototype. Problems: - Find a new user who has a different background and expertise on the system - Agregate and process large amount of input data to identify problems and improve design - Mathematical calculations of quantitative data requires a lot of efforts - Team members delay the testing schedule, which makes it hard to accumulate the data on time - Trying not to defend the design flaws against the users Future plans: - List out all the usability problems after analysis - Prioritize the problems - Discuss possible ways...

Status Report: (Test Plan)

For this update we focused on the specific details of the test plan for our project. We all spent time on the test document, here are the sections broken down: Toni Tran : Appendix A. User Requirements, General Test Plan Detailing (1.5 hours) Timothy Geary : General Test Plan Detailing (1.5) Alden Reed: General Test Plan Detailing (1.5 hours) Sean Bashaw : Appendix B, General Test Plan Detailing (1.5 hours) During the next week we plan to do our participant testing. We hope to get all tests done by the beginning of next week. There were no major challenges, or issues regarding this update.

Status Report: Deliverable 7 (High Fidelity Prototype)

For this deliverable, we developed a high fidelity prototype of our software. Here are our contributions: Tim : Created main layout of video editor, also created tools tab. (4 hours) Sean : Created videos tab (2 hours) Toni : Created chat tab (2 hours) Alden : Created share tab (2 hours) Challenges: One of the main challenges for this deliverable was finding times to meet up to work on each of the deliverables. In the future we hope to allocate more time for prototype developmentation. Issues: Some issues when adding videos to the videos tab by using the plus button. In the future: We plan to meet over the weekend to develop our test plan in concrete details.

Status report for deliverable 6

In this deliverable 6, we have 2 people from other teams test our interface design. We also send out 2 teammates to test another team's design. We fill out an evaluation form describing in details of how the 2 users interact with our design within 5 tasks, and discover a list of problems that we need to improve upon. Alden Reed, Sean Bashaw: observing 2 users from other team interacting with the design Toni Tran, Tim Geary: testing the design of another team Problems: - Some of the tool icons are difficult to understand, and may need better labels. - The "add video" button is hard to recognize - "Drag and drop video" feature needs clear instructions for first-time users Future plans: - Review a list of problems the users bring up - Resolve those problems in our next design - Keep/improve appraised design elements - Program our high fidelity prototype with JavaScript, HTML and CSS

Status Report for Deliverable 5

For deliverable 5 we have completed a more in-depth view of our design. This includes using marvel in order to create a more interactive version of our original wireframe, as well as deciding on key factors of our design as a group. We decided to all work on the main view of the video editor, and then we each took a different tab and fleshed out a further in-depth view. Below is what each person worked on and how long they worked on the tabs. Each person was responsible for describing their rationales, and description for their own tab. All : Design for main view (video editor, audio/video timeline, tab view placement) (1 hour) Sean : Video Tab (2 hours) Alden : Tools Tab (2.5 hours) Timothy : Chat Tab (2.5 hours) Toni : Share Tab (2.5 hours) By Sunday we hope to have a website that is completely functional and has at least 10 tasks you are able to complete. This prototype will be built using HTML for the skeleton structure, CSS for design, Javascript for functionality, and Nod...